Infrastructure Projects

infrastructure track work

 

Every summer Ontario Northland undertakes critical infrastructure work along the railway to ensure we meet industry safety standards and continue to provide safe, reliable and efficient transportation services to communities and businesses in the North.

Our top priority is to mitigate disruptions to communities and businesses as much as possible as this work is completed.
Please see the list below for projects impacting your community.

By investing in our rail infrastructure, we are keeping supply chains strong, and contributing to economic development in the north.

 

TRACK PROGRAM SCHEDULE

Community

Nature of Work

Schedule

Anticipated Community Impact

Marten River

Bolted rail replacement construction activities along rail right of way.

May, 2023

Temporary construction to take place overnight.

Minor noise disturbance is expected.

Moosonee

New siding construction activities along rail right of way.

May - June 2023

Temporary construction to take place overnight.

Minor noise disturbance is expected.

Swastika

 

Continuous welded rail (CWR) replacement construction activities along rail right of way.

 

June 13-21
 

Temporary construction to take place overnight. 10pm-8am.

Minor noise disturbance is expected.

North Bay Yard Work
(in proximity to Remanufacturing and Repair Centre)

Continuous welded rail (CWR) replacement construction activities along rail right of way.

June 6 - June 21

Temporary construction to take place overnight until approximately 12am.

Minor noise disturbance is expected.

North Bay and area Continuous welded rail (CWR) replacement construction activities along rail right of way. June 13-June 21

Temporary construction to take place overnight.
10pm-8am.

Minor noise disturbance is expected.

Virginiatown / Lac-Fortune

Continuous welded rail replacement construction activities along rail right of way.

June 6 -  21

Temporary construction to take place overnight.
10pm-8am.

Minor noise disturbance is expected.

Porquis
Cochrane

Tie replacement construction activities along rail right of way

July - August 2023

Temporary construction to take place overnight.

Minor noise disturbance is expected.

Ramore
Matheson
Connaught 

Bolted rail replacement construction activities along rail right of way.

 

Expected date of completion August 11, 2023

Temporary construction to take place overnight.

Minor noise disturbance is expected.

Smooth Rock Falls

Relay rail replacement construction activities along rail right of way.

August – September 2023.

Temporary construction to take place overnight.

Minor noise disturbance is expected.

Smooth Rock Falls
Fauquier
Moonbeam

Tie replacement construction activities along rail right of way

August - September 2023.

Overnight work expected to be completed August 16, 2023

Temporary construction to take place overnight.

Minor noise disturbance is expected.

 

BRIDGE REPAIR WORK

Community

Nature of Work

Schedule

Anticipated Community Impact

Nelles Creek (Hearst)

Bridge Repair

May 2023

Minimal noise disruption.

No road closure.

White Clay River, Bourkes

Bridge Repair

May - October, 2023

Minimal noise disruption.

No community in close proximity.

Kendall Creek (Hearst)

Bridge Repair

June-October, 2023

Minimal noise disruption.

No road closure.

Store Creek

Bridge Deck

July – September, 2023

Minimal noise disruption.

No road closure.

Kwatabohegan River, Moosonee

Bridge Repair

August – December, 2023

Minimal noise disruption.

Maidman’s Creek, Moosonee

Bridge Repair

August – December, 2023

Minimal noise disruption.

 

CULVERTS AND MAINTENANCE

Community

Nature of Work

Schedule

Anticipated Community Impact

Porquis - South Porcupine Brush clearing and tree removal. June, 2023 Minimal, temporary  noise disruption.
Cochrane - Smooth Rock Falls Brush clearing and tree removal. June, 2023 Minimal, temporary  noise disruption.

Ramore (Kirkland Lake)

Brush clearing and tree removal.

August, 2023

Residents may notice increased visibility to the track, in response to the brush clearing and tree removal.

 

WARNING SYSTEM UPGRADES

Community

Nature of Work

Schedule

Anticipated Community Impact

Broadwood (New Liskeard)

Mechanical upgrades to warning system

September 5, 2023

No anticipated impact.
Road will remain open with minimal disruption to traffic.

Whitewood (New Liskeard)

Mechanical upgrades to warning system

September 5, 2023

No anticipated impact.
Road will remain open with minimal disruption to traffic.

D'Amours Road (Moonbeam)

Mechanical upgrades to warning system

September 11, 2023

No anticipated impact.
Road will remain open with minimal disruption to traffic.

Tenth Street (Earlton)

Mechanical upgrades to warning system

September 5, 2023

No anticipated impact.
Road will remain open with minimal disruption to traffic.

Hopkin Road (Irquois Falls)

Mechanical upgrades to warning system

September 11, 2023

No anticipated impact.
Road will remain open with minimal disruption to traffic.

Frederickhouse Lake Road (Barber's Bay) Mechanical upgrades to warning system September 11, 2023 No anticipated impact.
Road will remain open with minimal disruption to traffic.
Hwy 11 Crossing (Hearst) Mechanical upgrades to warning system Complete Temporary lane closures between 8am and 4pm

If you have any questions or concerns about the work being undertaken, please reach out to 1(705) 472-4500 or pr@ontarionorthland.ca.